average wind speed: 6,95 m/s on the 100m height level
status: issued Building Permit in force
Project B:
capacity: 100MW
location: 85 km from the Baltic Sea coast line
average wind speed: 6,90 m/s on the 100m height level
status: issued Grid Connection Conditions, Grid Connection Agreement, Master Plan in force, completed basic design, issued Decisions of the Public Purpose Investment, completed EIA (Environment Impact Assessment), expected timing to receive Building Permit in force – March 2014
Project C:
capacity: 67,5MW
location: 40 km from the Baltic Sea coast line
average wind speed: 6,70 m/s on the 100m height level
status: issued Grid Connection Conditions, Grid Connection Agreement, Master Plan in force, completed basic design, issued Decisions of the Public Purpose Investment, completed EIA (Environment Impact Assessment), expected timing to receive Building Permit in force – March 2014
Project D:
capacity: 89,1MW
location: 25 km from the Baltic Sea coast line
average wind speed: 7,05 m/s on the 100m height level
status: issued Grid Connection Conditions, Grid Connection Agreement, Master Plan in force, completed basic design, issued Decisions of the Public Purpose Investment, completed EIA (Environment Impact Assessment), expected timing to receive Building Permit in force – March 2014
Project E:
capacity: 75MW
location: 60 km from Wrocław City
average wind speed: 6,8 m/s on the 120m height level
status: issued Grid Connection Conditions, Grid Connection Agreement, Master Plan in force, completed basic design, issued Decisions of the Public Purpose Investment, completed EIA (Environment Impact Assessment), expected timing to receive Building Permit in force – March 2014
Project F:
capacity: 6MW
location: 70 km from the Gdansk Harbor coast line
average wind speed: 6,8 m/s on the 100m height level
status: issued Building Permit in force
Project G:
capacity: 6MW
location: 80 km from the Baltic Sea coast line
average wind speed: 6,9 m/s on the 100m height level
status: issued Grid Connection Conditions, Grid Connection Agreement, Master Plan in force, completed basic design, issued Decisions of the Public Purpose Investment, completed EIA (Environment Impact Assessment), expected timing to receive Building Permit in force – May 2014